Construction of New Arena
Click on Pictures Below for Larger View!
June 30, 2006
Pouring foundation for west wall
July 12
First steel arrives
July
17
First steel goes up
July 27
All main rafters up
August 11
Some steel siding installed
August 23
More roof and sides done
September 1
Roof is done
September 1
Dressing rooms and
stands taking shape
September 8
Front taking shape
September 15
Front almost done
September 15
The floor is ready for concrete
September 22
Front almost complete
September 28
New color scheme for front
October 30
Ice being formed,
Skating on Nov. 1
October 30
Stands almost complete
November 10
Corridor for dressing
rooms 1 & 2
November 10
Dressing Room #1
November 10
Stands with plank seats
November 13
Door to public washrooms and
first aid
November 14
lobby area for public washrooms
November 15
Front Entrance