Update on New Construction
The demolition
got started on April 7, 2006 when the Sports Association and
volunteers removed the green steel siding, the glass around the
boards, the ice surface lights and other items. By April 12, all
this stuff, as well as, the Zamboni and canteen equipment were moved
out of the Arena and either sold or stored at pre-arranged
locations.
Bulldog Demolition were awarded a demolition contract of $65,500
plus GST to knock down the Arena and haul all the materials away.
They started on April 13 and were finished by April 26th.
Tenders closed for the Phase 1 - Construction on April 19. This work
would involve site preparation, footings and foundations, and the
full outer shell of the new arena complete with insulation and
exterior doors. This contract was awarded to Perry's Construction
for $866,000 plus GST. As of April 20, 2006, the steel beams were
ordered with a delivery date of early July. Perry's Construction is
waiting on shop drawings for the steel before they can start site
preparation and positioning the footings for the columns of the
steel roof beams.
The next phase, including the dressing rooms, canteen, other rooms,
electrical, mechanical (with plant room) and ice pad will be out to
tender by the week of May 22, 2006 and will close by June 5, 2006
Perry's
Construction has indicated they will be starting site work on June
5th 2006.
June 5, 2006 - Perry's Construction has started
construction on footings and foundation for the outside wall of the
Arena.
July 6, 2006 -
The Footings and Foundation will be complete by Friday, July 7th.
Perry's Construction is presently excavating the clay from around
the sand base for the ice surface. After adding more sand to
increase the length and width of the sand base (since the ice
surface is increasing to 200' long and 85' wide), Perry's will
replace the excavated areas that are left with the proper quality
fill.
The structural steel is due to be delivered from Ontario between
July 10 - 14th. The sub-contractor, Star Construction, will probably
start erecting the steel by July 17th -(See
page of Construction Pictures.)
The contract for
Phase II - Constructon was awarded to Perry's Construction for
$1,934,800 plus GST. Phase II includes all interior work.
Some
sub-contractors are:
-
MCM Bricklayers
Ltd. - Concrete Block
-
Summerside Industrial
Fabricators - Interior Structural steel and other metals
-
CIMCO - Refrigeration (Ice
Plant)
-
Red Isle Plumbing and Heating -
Mechanical
-
Gaudet's Electrical Service -
Electrical
-
The Paint Man - Painting
-
SEACOR – Dasher Boards
July 31 -
Summerside Industrial Fabricators began installing steel beams
between the columns to support the steel framework for the stands.
August 1 - Red Isle Plumbing installed the under floor sewer
connections for dressing rooms.
August 2 - Maritime Electric installed a new electrical service from
Phillip Street to serve the Arena and Legion. (Old service came in
from Chruch Street across other properties.)
August 3 - Star Construction started erecting the steel siding and
insulation on the east wall. The color of the steel side walls is
bone white with some red (for farming) and blue (for fishing) on the
front.
August 3 - Perry's Construction is constructing the Header Trench
for the piping in the ice surface.
August 10 – Perry’s Construction started pouring the floors for the
eight dressing rooms, all with in floor heating. Only six will be
built now along the left (east) side. The remaining two will be
built in future years.
The completion
date is still set for October 31st. This means that the ice surface
concrete has to be poured by October 1st, because the concrete has
to set for 30 days before making ice.
-
August 17 – MCM
started laying the concrete blocks for the dressing rooms.
-
August 23 – The roof
is half covered.
-
August 23/24 – Perry’s
Construction has completed the foundation in front as well as
erected the two columns to hold the canopy over the entrance.
-
August 25 –
Miscellaneous items – Red Isle Plumbing has completed the under
the floor plumbing across the front for the dressing room,
washrooms, and canteen. Gaudet’s Electric has installed the
underground conduit for electricity and telephone from the
Maritime Electric pole to the transformer pad and into the
building. Perry’s Construction installed a new two inch water line
to the Arena from the Municipal water System.
-
August 28 – Summerside
Industrial Fabricators started to install support beams for the
stands.
-
August 29 – Gaudet’s
Electrical installed and powered up the parking lot lights.
-
September 7 – Cimco
and Perry’s started to install the pipes, insulation, vapor
barrier and rebar for the ice surface. Plans are to pour the
concrete for the ice surface on Friday, September 15th.
-
September 8 –
Cameron Masonry started their phase I work of erecting the
concrete block wall across the front of the arena.
-
September 18 – The ice
surface floor was poured today. Perry’s
Construction and Summerside Industrial Fabricators continue to work
on the stands. Perry’s hope to pour the concrete for the stands on
September 21st. Star Construction
is working on the canopy over the front entrance. CIMCO has
completed the header pipes. They will be installing the two
compressors, chiller, and condenser along with the necessary
connections. Red Isle Plumbing
and Heating are working on water lines to washrooms, canteen, and
in-floor heating. They have to install two furnaces and two oil
tanks. Gaudet’s Electric
is setting up the electrical room inside the plant room. They’ll
soon have power to various sections of the arena. Next big job is to
install lights above the ice surface. The paint man
should be painting the rafters within the next 2 weeks.
-
September 19 – MCM
Bricklayers are finishing up the block walls around the Zamboni
and other side rooms. They still have the Entrance and Canteen
area to complete.
-
September 21 –
Summerside Industrial Fabricators started working on the upper
viewing room above the canteen.
Red Isle Plumbing and Heating are working on the two hot water
furnaces.
MCM Bricklayers are laying concrete blocks for the canteen and
elevator shaft.
-
September 28 – the
exterior front is complete except for the glass and steel
entrance, the roof fan for the canteen, some exterior lights, and
the Arena name.
-
October 2 – The Paint
Man started painting the ceiling and walls.
- SEACOR began installing the Dasher Boards
- Summerside Industrial Fabricators are installing the stairways
up to the stands
-
October 16 –
-
The stands are
almost complete except for cement on the lowest level and on
the stairways. The railings on the front and the stairways
still have to be installed.
-
The dressing rooms
are painted and Perry’s Construction is working on installing
the ceilings.
-
Maritime Electric
brought the power into the Arena’s Electrical Room on October
6 and dismantled the exterior temporary power pole on October
11.
-
CIMCO has
connected the two compressors, chiller and condenser together.
The chiller still has to be connected to the header pipes.
There is a heat recovery system to preheat the water for the
water heaters and furnaces.
-
Gaudet’s
Electrical has installed most of the necessary conduits with a
lot of wire to be pulled through them. Half the lights (22)
have been installed over the surface.
-
SEACOR is
installing the ice boards. They complete the posts and rough
framing. Next is the white material on the ice side and the
top for the boards. Then comes the glass and the netting up to
the ceiling.
-
The Pavement in
front of the building has been repaired. The road to the
Zamboni Room still has to be constructed. Perry’s Construction
still has some landscaping to complete.
-
Due to the
lateness of our project it was decided to delay the
installation of the elevator (although the pit and shaft are
there) and the construction of the parking lot area that was
leased from the Legion.
-
Red Isle Plumbing
continues to be on schedule with the heating and washroom
facilities.
-
MCM Bricklayers
are almost done except for a wall around the stairway to the
upper viewing room and around a door in the upper level.
-
Summerside
Industrial Fabricators continue their work on the stand
railings and on the upper viewing room.
-
The stands are
ready except for the charcoal painted two by twelve plank to
sit on and a sealer coat on the concrete.
-
Rink boards are
almost finished. Just a few more top plates by the Zamboni
door and the glass on the right (west) side.
-
Perry's
Construction installed a concrete pad outside the Zamboni
room to allow the ice shavings to be discarded.
-
The ice surface
lights are installed. They are being used as work lights.
-
The
refrigeration plant was turned on today. Because the
concrete floor is new, its temperature can only be lowered
by 4 deg F. every 8 hours. Should have ice by Oct. 31st.
-
Painting of
ceiling and walls is complete. Just a final coat for
dressing rooms and other interior rooms.
-
Bathroom
fixtures are ready to be installed.
-
Scoreboard-clock
was installed on the end wall.
-
MCM Bricklayers
are done of their work.
-
Summerside
Industrial Fabricators have the upper viewing room to
complete.
-
The glass and
steel main entrances (two of them) were installed October
26th and 27th.
-
Perry's are
working on the players' benches and penalty box.
-
The furnaces are
almost ready. Just the oil line and a few more pipes to
connect.
-
The asphalt
patching has been completed around the front of the Arena.
-
The cupboards
for the canteen are being built.
-
The rink opened
for the public on Nov.1 with a free skate. The first game was
the Atom AAA beating Summerside 6 to 5 on Nov. 2. The Senior
ACES played home on Nov. 10 beating O’Leary 9 to 4. The Midget
AA played Nov. 11 tying Morell 2-2. The Minor Juniors played
North River beating them 8-0.
-
Work
continues on the upper viewing room, men’s washroom, referees’
room, skate sharpening room, and refrigeration plant.
-
There are 12 fire
exits from the Arena plus the garage door in the zamboni room.
There are 28 emergency lights installed around the Arena. A
few more yet to be put in.
-
Most of the plank
seats are installed on the stands.
-
The rink boards,
netting, players’ benches, and penalty box are complete.
-
The heat is on.
Nice and warm in dressing rooms and public washrooms. Little
cool in canteen and manager’s office.
-
Canteen is in full
operation.
-
Still more light
fixtures to go up above the stands.
-
Arena is almost
complete. Perry’s Construction still has one employee
finishing up small details and Gaudets’s Electric is finishing
up their remaining items.
-
The upper viewing
room is complete with kitchen, 2 washrooms, storage room, and
sound room for the Figure Skating Club. See picture later on the
this page.
-
The Grand Opening
is tentatively set for Saturday, January 13, 2007 which is
Hockey Day in Canada on CBC. Tignish was selected as one of 5
locations across Canada where CBC will set up remote satellite
transmissions to broadcast short segments from Tignish at
various times throughout the day.
-
The canvassers
will be campaigning again January 6th trying to raise more
funds. We need approximately $270,000 more to meet our goal of
$1,066,666. Check other areas of our website for more
information on the Campaign.
-
A viewing area for
wheelchairs will be located at one of the corner boards on the
bleacher side of the rink.
-
The Lettering for
the Arena’s name is on order and hopefully will be installed
by January 13th. (the lighting for the name is already
installed.) Official name to be announced at the Grand
Opening.
Pictures Chronologically
Arranged
From Old to New
Click here for Pictures of Demolition of Old Arena
Click here for Pictures of
Construction Phase